Project Overview
The square will become a ‘space for everybody’ accessible and exciting for the whole community, including families, tourists, young professionals and the elderly.
The regeneration of Market Square will also be a trigger for the regeneration of surrounding buildings and their associated ground floor uses, this activation will encourage spill out into the square.
Transformation works started in February 2023, with estimated completion summer 2024.
Programme
- Public consultation – January 2022
- Works start on site – February 2023
- Works finish – Summer 2024
- Project opening – Autumn 2024
Funding
- £8,460,000 Future High Street Fund
- £2,000,000 S106 / CIL
Latest Updates
Milestones
- Planning Approval – December 2022
- Enabling works – Feb 2023 to April 2023
- Construction works commenced – April 2023
- Market Traders return – September 2024
- Opening event – October 2024
Press releases
- Section of regenerated paving opens at Northampton’s historic market square – March 2024
- Northampton’s Market Square contractors invest in local community – February 2024
- Northampton’s Market Square contractors invest in local businesses – February 2024
Photo updates
Below you can see the latest progress on site at the Market Square